Bullet Train Project: 10th Steel Bridge Completed in Ahmedabad
13 Oct, 2025

Bullet Train Project: 10th Steel Bridge Completed in Ahmedabad

The Mumbai–Ahmedabad Bullet Train project has achieved another milestone with the successful launching of its 10th steel bridge in Ahmedabad, Gujarat. The 60-meter-long bridge was installed over a Western Railway facility (laundry) situated adjacent to existing railway tracks. 

Following several months of detailed planning and logistical preparation, the bridge launching was executed with remarkable precision in just seven hours. This is the first steel bridge launched within the Ahmedabad district for the project.

For the transverse launching process, the bridge was pre-assembled at a height of 16.5 meters above ground level on temporary trestles. It was then side-slewed into its final position using two semi-automatic jacks, each with a 200-ton capacity, supported by locking trolleys to ensure stability and control.